Central Asia South Asia Electricity Transmission and Trade Project (CASA-1000)
Issues
Biodiversity
Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.
Complaints with this Issue: 134
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Central Asia South Asia Electricity Transmission and Trade Project (CASA-1000)
Investments: WB
Client:
Support: Loans
Complaint
ID: 93
Date Filed: April 21, 2014
Date Closed: July 31, 2014
Status: Closed Without Outputs
Complaint Stages
Filing
April 21, 2014
Filing
Status:
Start Date: April 21, 2014
Registration
April 21, 2014 -
July 31, 2014
Registration
Status: Closed With Output
Explanation: Outside of mandate, Inadequate link between bank action and harm alleged; Filer Issue, Not filed by project affected people
Eligibility
Not Undertaken
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
July 31, 2014
Timeline
Documents
Involved Groups
Name | Complaints | Group Type |
---|---|---|
Shark Ayoli | 1 | Local CSO |