Metro of Bogota First Line - First Tranch - Request II | Accountability Console
Complaints IAMs Register Login

Loading...

Metro of Bogota First Line - First Tranch - Request II

Issues

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 494

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Metro of Bogota First Line - First Tranch

Investments: IDB CO-L1234, IDB

Client:

Support: Loans

Country: Colombia

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-BID-CO-2021-0174

Date Filed: Sept. 7, 2021

Date Closed: Sept. 9, 2021

Status: Closed Without Outputs

Description

The Request describes a potential damage to the Requester’s living conditions and property, derived from the expropriation of his commercial property (automotive service station) for the construction of the Project. The Requester alleges that an alleged incorrect appraisal of his property would have been made, since the fair price would be lower than the market price, in addition to not considering the loss of profits due to the closing of the business, which would also have an impact on more than 20 people who work there. Finally, the Request cites a potential breach of the Project's General Resettlement Plan, which it is alleged that does not adhere to OP-710 Policy on Involuntary Resettlement.

Complaint Stages

Filing

Sept. 7, 2021

Filing

Status:

Start Date: Sept. 7, 2021

Registration

Closed Without Output

Registration

Status: Closed Without Output

Explanation: Good faith requirement not met

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Sept. 9, 2021

Timeline