Yunnan Lincang Border Economic Cooperation Zone Development Project
Issues
Procurement
Description: Complaint raises concerns about the process for obtaining goods or services related to the project. Most IAMs cannot address procurement concerns.
Complaints with this Issue: 79
Sectors
Community capacity and development
Description: Project relates to programs targeted at training, capacity-building, and/or enabling public participation for specific groups within the community.
Complaints in this Sector: 112
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Yunnan Lincang Border Economic Cooperation Zone Development Project
Investments: ADB 3759-PRC
Client:
Support: Loans
Country: China
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: None
Date Filed: June 21, 2021
Date Closed: June 21, 2021
Status: Closed Without Outputs
Complaint Stages
Filing
June 21, 2021
Filing
Status:
Start Date: June 21, 2021
Registration
June 21, 2021 -
June 21, 2021
Registration
Status: Closed Without Output
Explanation: Forwarded to other body within bank; Outside of mandate, Raised procurement issues
Eligibility
Not Undertaken
Eligibility
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
June 21, 2021
Timeline