Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

99 Results

Showing Only ADB Special Project Facilitator and Compliance Review Panel (Show All Results)

Top Results By:

  1. Complaint > North Eastern Region Capital Cities Development Investment Program

    Filing: Complaint

    ...request you to kindly take immediate note and action to safeguard us from extinction. Thanking You Yours Faithfully, Agnes Kharshiing, President of the CSWO(Civil Society Women’s Organization) Bomfyle Road, Laitumkhrah, Shillong, Meghalaya, India. Copy to the : Mr. A Joshi, Director (UD), MOUD, New delhi -110001, India. Mr. P.Naik IAS, Principal secy, UAD, Government of Meghalaya, Mr. Sultan Hafeez Rahman, Director General , SARD, ADB, HQ ...

    ADB Special Project Facilitator and Compliance Review Panel - India - 2011
  2. Complaint > Melamchi Water Supply Project (MWSP)

    Eligibility: Report on Eligibility

    ...Request contains the requisit~ basic information. In accordance with paragraph 30 of the CRP Operating Procedures, the CRP on this date has re~listered this Request as Request No. 2004/2 in the CRP Registry at www.comDliance.adb.o~ and has issued a press advisory on the registration of the Request. All communications with the Requesters in connection with the Request will be made until further notice with the following persons at the following address: Mr. Gopal Siwakoti, Coordinator, WAFE...

    ADB Special Project Facilitator and Compliance Review Panel - Nepal - 2004
  3. Complaint > Melamchi Water Supply Project (MWSP)

    Registration: Notice of Registration

    ...Request contains the requisit~ basic information. In accordance with paragraph 30 of the CRP Operating Procedures, the CRP on this date has re~listered this Request as Request No. 2004/2 in the CRP Registry at www.comDliance.adb.o~ and has issued a press advisory on the registration of the Request. All communications with the Requesters in connection with the Request will be made until further notice with the following persons at the following address: Mr. Gopal Siwakoti, Coordinator, WAFE...

    ADB Special Project Facilitator and Compliance Review Panel - Nepal - 2004
  4. Complaint > Integrated Citarum Water Resources Management Investment Program 2

    Compliance Report: CRP Final Report (English)

    ...request for compliance review related to these evictions. III. REQUEST FOR COMPLIANCE REVIEW 9. The OCRP received the request for compliance review of the ICRWMIP project on 30 January 2012 (Appendix 1). Hamong Santono of the nongovernment organization (NGO) People’s Alliance for Citarum (ARUM) signed the request letter under the letterhead of the People’s Coalition for the Right to Water (KRUHA), a member of ARUM.7 The three requesters explicitly sought to keep their identities confiden...

    ADB Special Project Facilitator and Compliance Review Panel - Indonesia - 2013
  5. Complaint > Jalalpur Irrigation Project & Greater Thal Canal Irrigation Project

    Closing Report: Complaint Closing Report

    ...President: Sindh Abadkar Board) COMPLAINT CLOSING REPORT OF CONCERNED ADB PROJECT TEAM 5 February 2025 COMPLAINT CLOSING REPORT OF CONCERNED ADB PROJECT TEAM 5 February 2025 Annex 2: Response Matrix on Complaint dated 26 December 2021 (Senior Vice President) Sindh Abadgar Board Subject: Concerns of lower riparians on enhancing capacity of water utilization by developing canal system of Chaubara Branch and Jalalpur Irrigation System ADB Project No. 46528- 002 S Comment Commentary 1 Ex...

    ADB Special Project Facilitator and Compliance Review Panel - Pakistan - 2025
  6. Complaint > Visayas Base-Load Power Project

    Monitoring: 1st Annual Monitoring Report

    ...request for compliance review was submitted to the CRP by the requesters, who were represented by Aaron Pedrosa Jr., secretary general of the Freedom from Debt Coalition chapter in Cebu, and Vicente Obando. According to the request, the power plant project had or was likely to have adverse effects on the health of the people living near the plant because (i) the emission of carbon dioxide (CO2), sulfur dioxide, and nitrogen dioxide could cause respiratory illnesses; (ii) the spillage of coa...

    ADB Special Project Facilitator and Compliance Review Panel - Philippines - 2013
  7. Complaint > Visayas Base-Load Power Project

    Monitoring: 4th Annual Monitoring Report

    ...requesters, submitted a request for compliance review to the CRP. According to the request, the KSPC power plant project had or was likely to have adverse effects on the health of the people living near it because of (i) its emission of carbon dioxide (CO2), sulfur dioxide, and nitrogen dioxide which could cause respiratory illnesses; (ii) the spillage of coal during transport exposing the community to hazardous, toxic metallic elements; and (iii) the seepage of harmful elements from the B...

    ADB Special Project Facilitator and Compliance Review Panel - Philippines - 2016
  8. Complaint > Visayas Base-Load Power Project

    Monitoring: 2nd Annual Monitoring Report

    ...requesters, submitted a request for compliance review to the CRP. According to the request, the KSPC power plant project had or was likely to have adverse effects on the health of the people living near it because of (i) its emission of carbon dioxide (CO2), sulfur dioxide, and nitrogen dioxide which could cause respiratory illnesses; (ii) the spillage of coal during transport exposing the community to hazardous, toxic metallic elements; and (iii) the seepage of harmful elements from the B...

    ADB Special Project Facilitator and Compliance Review Panel - Philippines - 2014
  9. Complaint > National Highway Development Sector Investment Program

    Eligibility: Pre-Eligibility Screening Report

    ...Request for Change of Alignment: A request for changing the alignment of the Bypass from the designed alignment to that suggested by the complainants has been repeatedly made by the complainants to the Chairman, NHA. They have not been informed in writing about the fate of their request. However, the project-affected people feel that fixing of boundary marking pillars or burjis4 for the alignment of the Muzaffargarh Bypass and publication of notice for acquisition of land in the Punjab Gaze...

    ADB Special Project Facilitator and Compliance Review Panel - Pakistan - 2006
  10. Complaint > Phnom Penh to Ho Chi Minh City Highway Project

    Dispute Resolution: Final Report

    ...request for comments, and the complainants' request to postpone the consultation process, were dispatched on the same day and crossed enroute to their destinations. 9 ADB. 2009. Kingdom of Cambodia: Capacity Development for Income Restoration Programs. Manila (TA 7366- CAM). http://www.adb.org/Projects/project.asp?id=43174

    ADB Special Project Facilitator and Compliance Review Panel - Cambodia - 2010
  11. Complaint > Melamchi Water Supply Project (MWSP)

    Dispute Resolution: Final Report, 22 Dec 2004

    ...President, Vice-President (Operations 1), SARD and the complainants on 28 June 2004. The complainants were very critical of the RAR, alleging that it was biased in favor of the Government and ADB. They also strongly disagreed with SPF’s position that reopening a debate on the original MWSP design was outside SPF’s mandate. Notwithstanding their disagreement with SPF’s review and assessment, the complainants decided to carry on with the consultation process. 23. At step 6 of the consul...

    ADB Special Project Facilitator and Compliance Review Panel - Nepal - 2004
  12. Complaint > Integrated Citarum Water Resources Management Investment Program 2

    Dispute Resolution: Review and Assessment Report (English)

    ...President, the resettlement framework and plan, back-to-office reports, memoranda of understanding, the periodic financing request for project 1, and terms of reference ; (ii) interviews and meetings with ADB staff and consultants previously and currently involved in the project; (iii) interviews with BAPPENAS, DGWR, BBWSC, and the local government of the District of Bekasi; (iv) a meeting with Perum Jasa Tirta II (PJT II, the state-owned company managing the WTC); (v) interviews and meetin...

    ADB Special Project Facilitator and Compliance Review Panel - Indonesia - 2011
  13. Complaint > Southern Transport Development Project (STDP)

    Monitoring: Annual Monitoring Report [PDF]Report sent to Requesters

    ...request for compliance review (Request) on the Southern Transport Development Project1 (STDP or Project) in Sri Lanka. The Request was submitted by the Joint Organization of the Affected Communities of the Colombo Matara Highway (Requesters). The CRP determined that the request was eligible, and the Board of Directors (Board) of the Asian Development Bank (ADB) authorized the CRP to conduct a compliance review. The Panel reviewed and investigated the request and submitted to the Board its ...

    ADB Special Project Facilitator and Compliance Review Panel - Sri Lanka - 2007
  14. Complaint > Shapoorji Affordable Housing Project

    Eligibility: Eligibility Report

    ...Request for Compliance Review 6 2. ADB Management’s Response 24 I. BACKGROUND 1. A request for compliance review (complaint) was forwarded by the Complaint Receiving Officer of the Asian Development Bank (ADB) Accountability Mechanism to the Compliance Review Panel (CRP) on 3 March 2022 in respect of private sector investment, ADB Equity No. 7452: Shapoorji Affordable Housing Project (Project) in India. 1 2. In accordance with para. 178 of the Accountability Mechanism Policy (AMP) read w...

    ADB Special Project Facilitator and Compliance Review Panel - India - 2022
  15. Complaint > Education Sector Reform Project

    Dispute Resolution: Final Report (English)

    ...President to the Board of Directors: Proposed Loan to the Republic of Tajikistan for the Education Sector Reform Project. Manila. Loan 2053-TAJ. vi I. BACKGROUND A. The Project 1. The Education Sector Reform Project1 aimed to improve the quality, efficiency, and equity of primary and general secondary education. The Asian Development Bank (ADB) approved a loan of $7.5 million on 17 December 2003. The President’s Off...

    ADB Special Project Facilitator and Compliance Review Panel - Tajikistan - 2011
  16. Complaint > East-West Highway Improvement Project

    Filing: Complaint

    ...request Executing Agency to follow ADB policies and national legislations of Azerbaijan. We request you to immediately intervene in this situation to provide assistance to the affected communities on above mentioned problems and concerns. Complain letter from APs is attached. Please, we request you not to disclose the names of complainers per their request due to their fear of intimidation and harassment from the executing agencies. Looking forward to hear from you soon, Zohrab Ismayi...

    ADB Special Project Facilitator and Compliance Review Panel - Azerbaijan - 2009
  17. Complaint > National Highway Development Sector Investment Program

    Dispute Resolution: Review and Assessment report (RAR)

    ...requested NHA and CWID to consider a change in the alignment of the Bypass to avoid their houses and other properties to be destroyed. They claim that they have not been informed about a decision regarding their request. However, they feel that the activities observed in recent months (i) fixing of boundary markers for the alignment of the Bypass; (ii) publishing in the Punjab Gazette of notice for acquisition of land; and (iii) fixing of notices at their residences effectively mean that th...

    ADB Special Project Facilitator and Compliance Review Panel - Pakistan - 2007
  18. Complaint > Visayas Base-Load Power Project

    Monitoring: 5th Annual Monitoring Report

    ...requesters, submitted a request for compliance review to the CRP. According to the request, the Project had or was likely to have adverse effects on the health of the people living near it because of (i) its emission of carbon dioxide (CO2), sulfur dioxide, and nitrogen dioxide which could cause respiratory illnesses; (ii) the spillage of coal during transport exposing the community to hazardous, toxic metallic elements; and (iii) the seepage of harmful elements from the Balili coal ash dum...

    ADB Special Project Facilitator and Compliance Review Panel - Philippines - 2017
  19. Complaint > Clean Energy and Network Efficiency Improvement Project

    Closing Report: Closure Report

    ...President to the Board of Directors: Multitranche Financing Facility to the Democratic Socialist Republic of Sri Lanka for the Green Power Development and Energy Efficiency Improvement Investment Program (Tranche 2). Manila. 16 ADB. 2017. Report and Recommendation of the President to the Board of Directors: Proposed Loan, Ceylon Electricity Board: Wind Power Generation Project (Guaranteed by the Democratic Socialist Republic of Sri Lanka. Manila 17 The Kegalle GSS also includes a 15 MVAr, ...

    ADB Special Project Facilitator and Compliance Review Panel - Sri Lanka - 2021
  20. Complaint > Southern Transport Development Project (STDP)

    Monitoring: Annual Monitoring Report [PDF]Report sent to Requesters

    ...request for compliance review of the Southern Transport Development Project1 (STDP or Project) in Sri Lanka. The request was submitted by the Joint Organization of the Affected Communities of the Colombo Matara Highway (requesters). CRP determined that the request was eligible, and the Board of Directors (Board) of the Asian Development Bank (ADB) authorized a compliance review by CRP. The Panel reviewed and investigated the request and submitted its findings and recommendations to the Boa...