Assam Power Transmission Improvement Project
Issues
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 387
Project
Name: Assam Power Transmission Improvement Project
Investments: ADB TA 9240-IND
Client:
Support: Advisory services
Country: India
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: None
Date Filed: June 13, 2018
Date Closed: June 14, 2018
Status: Closed Without Outputs
Complaint Stages
Filing
June 13, 2018
Filing
Status:
Start Date: June 13, 2018
Registration
June 13, 2018 -
June 14, 2018
Eligibility
Not Undertaken
Eligibility
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
June 14, 2018
Timeline