CA CCFL Reventazon Hydropower | Accountability Console
Complaints IAMs Register Login

Loading...

CA CCFL Reventazon Hydropower

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 134

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 482

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 482

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 342

Browse Complaints

Project

Name: CA CCFL Reventazon Hydropower

Investments: EIB 20120472

Client: Central Merican Bank for Economic Integration (BCIE/CABEI)

Support:

Country: Costa Rica

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2016/18

Date Filed: Sept. 28, 2016

Date Closed: July 17, 2019

Status: Closed With Outputs

Description

On 28 September 2016, the EIB Complaints Mechanism (EIB-CM) received a complaint concerning the Reventazín Hydroelectric project. The complainants are the owners of the Lancaster Farm, a 190 ha property located within the area of influence of the project. Lancaster Farm comprises various types of land uses, including two protected wetlands (‰ÛÏthe Lancaster Lagoons‰Û). The Lower Lancaster Lagoon is separated from the Reventazín River by an approximately 70 m high slope. The complainants have presented four main allegations: (i) non-compliance with the Banks standards concerning nature protection; (ii) failure to reconstruct the Mesoamerican Biological Corridor; (iii) non-compliance with the obligation to remove the vegetation from the reservoir area; and (iv) failure to conduct land acquisition in line with the Banks standards. The project consists of the construction of a new 305.5 MW hydroelectric plant with a large dam and a medium-sized reservoir on the Reventazín River in Costa Rica. The project is expected to contribute to climate change mitigation and security of electricity supply by providing hydropower to meet increasing demand for electricity in Costa Rica and the region.

Complaint Stages

Filing

Sept. 28, 2016

Filing

Status:

Start Date: Sept. 28, 2016

Registration

Sept. 28, 2016 -

Oct. 5, 2016

Registration

Status: Closed With Output

Start Date: Sept. 28, 2016

End Date: Oct. 5, 2016

Eligibility

Oct. 5, 2016 -

May 2, 2017

Eligibility

Status: Closed With Output

Start Date: Oct. 5, 2016

End Date: May 2, 2017

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Actor(s) involved refused to participate

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Start Date: None

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Closed With Output

Monitoring

Status: Closed With Output

Explanation: Unknown

Closed

July 17, 2019

Timeline

Documents

Name Category Description
Conclusions Report Compliance Review