Cairo Metro Line 3 (Phase 3)
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Cairo Metro Line 3 (Phase 3)
Investments: EIB 20100613
Client: National Authority for Tunnels (NAT)
Support: Loans
Country: Egypt
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2018/41
Date Filed: Nov. 5, 2018
Date Closed: June 30, 2021
Status: Closed With Outputs
Description
Complaint Stages
Filing
Nov. 5, 2018
Filing
Status:
Start Date: Nov. 5, 2018
Registration
Nov. 5, 2018 -
Nov. 12, 2018
Registration
Status: Closed With Output
Start Date: Nov. 5, 2018
End Date: Nov. 12, 2018
Eligibility
Nov. 5, 2018 -
July 4, 2019
Eligibility
Status: Closed With Output
Start Date: Nov. 5, 2018
End Date: July 4, 2019
Dispute Resolution
Not Undertaken
Compliance Review
July 4, 2019 -
Nov. 30, 2020
Compliance Review
Status: Closed With Output
Start Date: July 4, 2019
End Date: Nov. 30, 2020
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Nov. 30, 2020 -
June 30, 2021
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party
Closed
June 30, 2021
Timeline