Construction/Improvement 0f 5.34 Km. Visares-Barugo Farmto-Market Road
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Construction/Improvement 0f 5.34 Km. Visares-Barugo Farmto-Market Road
Investments: ADB
Client:
Support: Loans
Country: Unknown
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: None
Date Filed: June 27, 2012
Date Closed: July 31, 2012
Status: Closed Without Outputs
Complaint Stages
Filing
June 27, 2012
Filing
Status:
Start Date: June 27, 2012
Registration
June 27, 2012 -
July 17, 2012
Registration
Status: Closed With Output
Start Date: June 27, 2012
End Date: July 17, 2012
Eligibility
July 17, 2012 -
July 31, 2012
Dispute Resolution
Not Undertaken
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
July 31, 2012
Timeline