Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Eastern Poland Roads Ten-T
Issues
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2012/06
Date Filed: May 2, 2012
Date Closed: Jan. 18, 2013
Status: Closed With Outputs
Description
Complaint Stages
Filing
May 2, 2012
Filing
Status:
Start Date: May 2, 2012
Registration
May 2, 2012 -
May 2, 2012
Registration
Status: Closed With Output
Start Date: May 2, 2012
End Date: May 2, 2012
Eligibility
May 2, 2012 -
Aug. 15, 2012
Eligibility
Status: Closed With Output
Start Date: May 2, 2012
End Date: Aug. 15, 2012
Dispute Resolution
Not Undertaken
Compliance Review
Aug. 15, 2012 -
Jan. 18, 2013
Compliance Review
Status: Closed With Output
Start Date: Aug. 15, 2012
End Date: Jan. 18, 2013
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party
Closed
Jan. 18, 2013
Timeline