GMS Rehabilitation of the Railway in Cambodia Project
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: GMS Rehabilitation of the Railway in Cambodia Project
Investments: ADB
Client:
Support: Loans
Country: Cambodia
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: None
Date Filed: July 25, 2013
Date Closed: July 31, 2013
Status: Closed Without Outputs
Complaint Stages
Filing
July 25, 2013
Filing
Status:
Start Date: July 25, 2013
Registration
July 25, 2013 -
July 26, 2013
Registration
Status: Closed With Output
Start Date: July 25, 2013
End Date: July 26, 2013
Eligibility
July 26, 2013 -
July 31, 2013
Eligibility
Status: Closed Without Output
Explanation: Outside of mandate; Forwarded to other body within bank; Outside of mandate, Raised procurement issues
Dispute Resolution
Not Undertaken
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
July 31, 2013
Timeline