Greater Colombo Water and Wastewater Management Improvement Investment Program (Tranche 2) | Accountability Console
Complaints IAMs Register Login

Loading...

Greater Colombo Water and Wastewater Management Improvement Investment Program (Tranche 2)

Issues

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Unknown

Description:

Complaints with this Issue: 727

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Other

Description: Project relates to an industry that does not fit in one of the other sectors. Projects about which there is no publicly available information regarding the industry are also included.

Complaints in this Sector: 595

Browse Complaints

Description

Complaint raised issues of damaged roads and flooding.

Complaint Stages

Filing

Sept. 13, 2023

Filing

Status:

Start Date: Sept. 13, 2023

Registration

Sept. 13, 2023 -

Sept. 14, 2023

Registration

Status: Closed With Output

Start Date: Sept. 13, 2023

End Date: Sept. 14, 2023

Eligibility

Sept. 14, 2023 -

Oct. 11, 2023

Eligibility

Status: Closed Without Output

Explanation: Good faith requirement not met

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Oct. 11, 2023

Timeline