Integrated Citarum Water Resources Management Investment Program 2
Issues
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Sectors
Conservation and environmental protection
Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.
Complaints in this Sector: 62
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Integrated Citarum Water Resources Management Investment Program
Investments: ADB
Client:
Support: Loans
Country: Indonesia
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: SPF-2011-01-02-0033 & 2012/1
Date Filed: Jan. 4, 2011
Date Closed: Dec. 31, 2015
Status: Closed With Outputs
Complaint Stages
Filing
Jan. 4, 2011
Filing
Status:
Start Date: Jan. 4, 2011
Registration
Jan. 4, 2011 -
Jan. 10, 2011
Registration
Status: Closed With Output
Start Date: Jan. 4, 2011
End Date: Jan. 10, 2011
Eligibility
Jan. 10, 2011 -
Feb. 2, 2011
Eligibility
Status: Closed With Output
Start Date: Jan. 10, 2011
End Date: Feb. 2, 2011
Dispute Resolution
March 23, 2011 -
Feb. 23, 2012
Dispute Resolution
Status: Closed Without Output
Start Date: March 23, 2011
End Date: Feb. 23, 2012
Compliance Review
March 21, 2012 -
April 21, 2013
Compliance Review
Status: Closed With Output
Start Date: March 21, 2012
End Date: April 21, 2013
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
April 10, 2013 -
Dec. 10, 2015
Monitoring
Status: Closed With Output
Start Date: April 10, 2013
End Date: Dec. 10, 2015
Closed
Dec. 31, 2015
Timeline
Documents
Name | Category | Description |
---|---|---|
Compliance Reprt | Compliance Report | |
Monitoring Report | Monitoring |
Commitments
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Integrated Citarum Water Resources Management Investment Program | ADB SPF CRP | Indonesia | 08/12/2009 | Closed Without Outputs |