Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Kerala Sustainable Urban Development Project 3
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Kerala Sustainable Urban Development Project
Investments: ADB
Client:
Support: Loans
Country: India
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: None
Date Filed: March 5, 2013
Date Closed: March 31, 2013
Status: Closed Without Outputs
Complaint Stages
Filing
March 5, 2013
Filing
Status:
Start Date: March 5, 2013
Registration
March 5, 2013 -
March 6, 2013
Registration
Status: Closed With Output
Start Date: March 5, 2013
End Date: March 6, 2013
Eligibility
March 6, 2013 -
March 31, 2013
Eligibility
Status: Closed Without Output
Explanation: Outside of mandate; Forwarded to other body within bank
Dispute Resolution
Not Undertaken
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
March 31, 2013
Timeline
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Kerala Sustainable Urban Development Project | ADB SPF CRP | India | 17/10/2011 | Closed Without Outputs |
Kerala Sustainable Urban Development Project 2 | ADB SPF CRP | India | 14/08/2012 | Closed Without Outputs |