Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Santa Barbara-Rurrenabaque Northern Corridor Highway Improvement Program

Investments: IDB

Client:

Support: Loans

Country: Bolivia

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-BO-2011-013

Date Filed: Feb. 28, 2011

Date Closed: Dec. 31, 2014

Status: Closed With Outputs

Description

The “Foro Boliviano sobre el Medio Ambiente y Desarrollo” submitted a Request concerning the negative environmental and social impacts that the construction and access of a bridge connecting Rurrenabaque and San Buenaventura in Bolivia could cause to Rurrenabaque and its inhabitants. In addition, the Request alleged the inadequate management of information and of the public consultation process, during which the community’s concerns had not been addressed and the different designs of the bridge project had not been based on social, environmental and urban planning analyses by the Executing Agency, the “Administradora Boliviana de Carreteras” (ABC).

Complaint Stages

Filing

Feb. 28, 2011

Filing

Status:

Start Date: Feb. 28, 2011

Registration

Feb. 28, 2011 -

March 15, 2011

Registration

Status: Closed With Output

Start Date: Feb. 28, 2011

End Date: March 15, 2011

Eligibility

March 15, 2011 -

April 13, 2011

Eligibility

Status: Closed With Output

Start Date: March 15, 2011

End Date: April 13, 2011

Dispute Resolution

Aug. 24, 2011 -

April 24, 2013

Dispute Resolution

Status: Closed With Output

Start Date: Aug. 24, 2011

End Date: April 24, 2013

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Board did not approve, Board did not authorize

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

Dec. 31, 2014

Timeline