Nyamagasami 2 HPP Limited

Issues

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 508

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 355

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 1029

Browse Complaints

Project

Name: Nyamagasani 2 HPP Limited

Investments: FMO 51478

Client: Nyamagasani 2 HPP Limited

Support: Loans

Country: Uganda

Complaint

IAM: Independent Complaints Mechanism (ICM)

ID: 20-001, 20-003/add. complaint 1

Date Filed: Aug. 11, 2020

Date Closed: July 31, 2024

Status: Closed Without Outputs

Description

On 11 August 2020, the Panel received an additional complaint from an individual complainant (“Third Complaint”). The Panel, through the FMO Complaints Office, informed the complainant that his complaint will also be joined to the same case as the other two complaints concerning the same project. The Third Complaint was filed by a complainant whose land was allegedly acquired by the project. However, the project provided compensation to his son only for crops that were grown on that land by his son, despite him not being the legal owner of the land. (Source doc: Third Admissibility Notice for additional complaints, '2020-November | Notice of Admissibility Case no 2020-Nyamagasani 2 HPP Additional complaints'

Complaint Stages

Filing

Aug. 11, 2020

Filing

Status:

Start Date: Aug. 11, 2020

Registration

Aug. 11, 2020 -

Aug. 31, 2020

Registration

Status: Closed With Output

Start Date: Aug. 11, 2020

End Date: Aug. 31, 2020

Eligibility

Aug. 31, 2020 -

Nov. 12, 2020

Eligibility

Status: Closed With Output

Start Date: Aug. 31, 2020

End Date: Nov. 12, 2020

Dispute Resolution

June 1, 2021 -

March 31, 2022

Dispute Resolution

Status: Closed With Output

Start Date: June 1, 2021

End Date: March 31, 2022

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

March 31, 2022 -

July 31, 2024

Monitoring

Status: Closed With Output

Start Date: March 31, 2022

End Date: July 31, 2024

Closed

July 31, 2024

Timeline