Porto De Aveiro, Portugal | Accountability Console
Complaints IAMs Register Login

Loading...

Porto De Aveiro, Portugal

Issues

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Porto De Aveiro

Investments: EIB

Client:

Support:

Country: Portugal

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2011/16

Date Filed: Nov. 8, 2011

Date Closed: Oct. 12, 2012

Status: Closed With Outputs

Description

The complainant raised concerns regarding the design of the project, its environmental impacts and the strategic and economical choices made by the authorities regarding the project, notably concerning an improper design for the prolongation of the North jetty at the entrance of the port and important environmental impacts due to the inaccurate design.

Complaint Stages

Filing

Nov. 8, 2011

Filing

Status:

Start Date: Nov. 8, 2011

Registration

Nov. 8, 2011 -

Nov. 8, 2011

Registration

Status: Closed With Output

Start Date: Nov. 8, 2011

End Date: Nov. 8, 2011

Eligibility

Closed With Output

Eligibility

Status: Closed With Output

Start Date: None

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage; Unknown

Compliance Review

Nov. 8, 2011 -

Oct. 12, 2012

Compliance Review

Status: Closed With Output

Start Date: Nov. 8, 2011

End Date: Oct. 12, 2012

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party

Closed

Oct. 12, 2012

Timeline