Rawalpindi Environmental Improvement Project (Water Supply Component)
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Rawalpindi Environmental Improvement Project (Water Supply Component)
Investments: ADB
Client:
Support: Loans
Country: Pakistan
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: Aug. 13, 2009
Date Closed: Aug. 31, 2009
Status: Closed Without Outputs
Complaint Stages
Filing
Aug. 13, 2009
Filing
Status:
Start Date: Aug. 13, 2009
Registration
Aug. 13, 2009 -
Aug. 13, 2009
Registration
Status: Closed With Output
Start Date: Aug. 13, 2009
End Date: Aug. 13, 2009
Eligibility
Aug. 13, 2009 -
Aug. 31, 2009
Eligibility
Status: Closed Without Output
Explanation: Filer Issue, Not filed by project affected people
Dispute Resolution
Not Undertaken
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Aug. 31, 2009
Timeline
Documents
Name | Category | Description |
---|---|---|
Complaint received, 13 Aug 2009 | Filing | reip-2nd-complaint.pdf |