Regional Road Development and Maintenance Project
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Regional Road Development and Maintenance Project
Investments: ADB 48186-005
Client: Ministry of Road and Transport Development of Mongolia
Support: Advisory services, Grant, Loans
Country: Mongolia
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: May 27, 2022
Date Closed: June 23, 2022
Status: Closed Without Outputs
Description
Complaint Stages
Filing
May 27, 2022
Filing
Status:
Start Date: May 27, 2022
Registration
May 27, 2022 -
May 31, 2022
Registration
Status: Closed Without Output
Start Date: May 27, 2022
End Date: May 31, 2022
Eligibility
May 31, 2022 -
June 23, 2022
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
June 23, 2022
Timeline
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Regional Road Development and Maintenance Project | ADB SPF CRP | Mongolia | 08/05/2023 | Closed Without Outputs |