Spain Gas Network Expansion II
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Extractives (oil, gas, mining)
Description: Project relates to the extractive industries, including oil, gas, and mining. Examples may include mines, drilling operations, pipelines, and the associated legal frameworks.
Complaints in this Sector: 201
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2018/13
Date Filed: March 2, 2018
Date Closed: Sept. 20, 2019
Status: Closed Without Outputs
Description
Complaint Stages
Filing
March 2, 2018
Filing
Status:
Start Date: March 2, 2018
Registration
Feb. 8, 2018 -
Feb. 8, 2018
Registration
Status: Closed With Output
Start Date: Feb. 8, 2018
End Date: Feb. 8, 2018
Eligibility
March 2, 2018 -
May 14, 2019
Eligibility
Status: Closed With Output
Start Date: March 2, 2018
End Date: May 14, 2019
Compliance Review
May 14, 2019 -
Sept. 20, 2019
Compliance Review
Status: Closed Without Output
Explanation: Mechanism deemed involvement unnecessary; Funding and/or consideration ended; Outside of mandate, Project not implemented
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Sept. 20, 2019