Support for the Transmission System in Paraguay (PR-L1058) | Accountability Console
Complaints IAMs Register Login

Loading...

Support for the Transmission System in Paraguay (PR-L1058)

Issues

Procurement

Description: Complaint raises concerns about the process for obtaining goods or services related to the project. Most IAMs cannot address procurement concerns.

Complaints with this Issue: 79

Browse Complaints

Unknown

Description:

Complaints with this Issue: 727

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Description

The Request deals only with issues related to bidding processes.

Complaint Stages

Filing

Sept. 22, 2020

Filing

Status:

Start Date: Sept. 22, 2020

Registration

Sept. 22, 2020 -

Sept. 28, 2020

Registration

Status: Closed With Output

Explanation: Outside of mandate, Raised procurement issues

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Sept. 28, 2020

Timeline