Togo LCT-02/Lome

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 359

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 481

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 482

Browse Complaints

Labor

Description: Complaint raises concerns about violations of appropriate labor standards related to the project, including issues regarding compensation, workplace conditions, retaliation, and child or forced labor.

Complaints with this Issue: 101

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 344

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 226

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Project

Name: Togo LCT

Investments: IFC 29197

Client: Société Lomé Container Terminal

Support:

Country: Togo

Complaint

IAM: Compliance Advisor/Ombudsman (CAO)

ID: togo-togo-lct-02lome

Date Filed: Feb. 16, 2018

Status: Monitoring

Description

In February 2018, CAO received a complaint from the “Mouvement Martin Luther King – La voix des sans voix”. The complaint was signed by six affected individuals, who belong to a group of former sand miners and market gardeners. The complainants claim LCT’s operations are negatively impacting them, and a larger group of people.

The complainants allege that LCT has not respected its commitments in relation to the project’s Resettlement Action Plan (RAP), particularly with regards to affected groups of market gardeners and sand miners. They claim that the execution of the RAP did not respect the frameworks of the World Bank Group, or the other national and international legal frameworks, including the Togolese Constitution and the Universal Declaration of Human Rights (UDHR). The complainants further claim that the project has impoverished surrounding communities, and raise concerns regarding ambient pollution and health impacts to “marine sand drippers”, who worked on the site. The complaint also raises labor concerns, in particular with regard to hiring practices, dismissals, and wages of lashing operations personnel (“Lashingmen”).

Complaint Stages

Filing

Feb. 16, 2018

Filing

Status:

Start Date: Feb. 16, 2018

Registration

Not Undertaken

Registration

Status: Not Undertaken

Explanation: Not offered by mechanism, Stage is not practiced by mechanism

Eligibility

Feb. 16, 2018 -

March 31, 2018

Eligibility

Status: Closed With Output

Start Date: Feb. 16, 2018

End Date: March 31, 2018

Dispute Resolution

Aug. 1, 2018 -

Oct. 31, 2023

Dispute Resolution

Status: In Progress

Start Date: Aug. 1, 2018

End Date: Oct. 31, 2023

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Oct. 31, 2023

Monitoring

Status: In Progress

Start Date: Oct. 31, 2023

Closed

Not Closed

Timeline

Related Complaints

Project IAM Country Date Filed Status
Togo LCT-03/Lome IFC CAO Togo 20/12/2022 Active