Trans-Sahara Optic Fiber Backbone Project
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1078
Complaint
IAM: Independent Recourse Mechanism (IRM)
ID: None
Date Filed: June 29, 2020
Date Closed: June 29, 2020
Status: Closed Without Outputs
Description
Complaint Stages
Filing
June 29, 2020
Filing
Status:
Start Date: June 29, 2020
Registration
June 29, 2020 -
June 29, 2020
Registration
Status: Closed With Output
Explanation: Outside of mandate; Outside of mandate, Raised personnel issues
Eligibility
Not Undertaken
Eligibility
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered