Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Urban Transport Transformation Project
Issues
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Urban Transport Transformation Project
Investments: WB P107159
Client: United Mexican States, Banco Nacional de Obras y Servicios Publicos (S.N.C.)
Support:
Country: Mexico
Complaint
ID: 109
Date Filed: April 1, 2016
Date Closed: Aug. 3, 2016
Status: Closed Without Outputs
Description
Complaint Stages
Filing
April 1, 2016
Filing
Status:
Start Date: April 1, 2016
Registration
April 1, 2016 -
Aug. 3, 2016
Registration
Status: Closed With Output
Explanation: Outside of mandate, Inadequate link between bank action and harm alleged
Eligibility
Not Undertaken
Eligibility
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Aug. 3, 2016
Timeline