Vizhinjam-01/Kerala
Issues
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Vizhinjam-01/Kerala
Investments: IFC 28991
Client:
Support: Advisory services
Country: India
Complaint
IAM: Compliance Advisor/Ombudsman (CAO)
Date Filed: Aug. 21, 2012
Date Closed: June 23, 2020
Status: Closed With Outputs
Complaint Stages
Filing
Aug. 21, 2012
Filing
Status:
Start Date: Aug. 21, 2012
Registration
Not Undertaken
Registration
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Eligibility
Aug. 21, 2012 -
Sept. 1, 2012
Eligibility
Status: Closed With Output
Start Date: Aug. 21, 2012
End Date: Sept. 1, 2012
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Actor(s) involved refused to participate, Company or government refused to go through dispute resolution
Compliance Review
June 1, 2015 -
Jan. 1, 2018
Compliance Review
Status: Closed With Output
Start Date: June 1, 2015
End Date: Jan. 1, 2018
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
Jan. 1, 2018 -
June 23, 2020
Monitoring
Status: Closed With Output
Start Date: Jan. 1, 2018
End Date: June 23, 2020
Closed
June 23, 2020
Timeline
Documents
Involved Groups
Name | Complaints | Group Type |
---|---|---|
Kerala branch of Exnora International | 1 | Unknown |
People's Resistance Committee in Vizhinjam | 1 | Local Community Org |
Kerala Hotels and Restaurants Associtiation | 1 | Unknown |
Commitments
Type | Category | Description | Status |
---|---|---|---|
Process Change | Operations Management | New Environmental and Social Review Procedure | Accomplished |