Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.
3 Results
Showing Only Sostanj Thermal Power Plant (Show All Results)
Top Results By:
-
Complaint > Sostanj Thermal Power Plant
...President and the Board of Directors pursuant PCM RP 29. 7. Compliance Review Expert 15 January 2013 Dr Owen McIntyre appointed. 8. Eligibility Assessment 22 January 2013 Report is publicly released and posted on the PCM website pursuant PCM RP 29 (a). 9. Compliance Review Report 17 September 2013 sent to Relevant Parties, including the President and the Board of Directors for information pursuant PCM RP 39. 10. Compliance Review Report 23 September 2013 is pos...
EBRD Project Complaint Mechanism - Slovenia -
Complaint > Sostanj Thermal Power Plant
Compliance Report: Compliance Review Report
...Request No. 2011/05), para. 18; PCM, Compliance Review Report: Ombla Hydropower Project (Request No. 2011/06), para. 27. Indeed, the relevance of Article 6(3) of the 1992 Habitats Directive for the interpretation of Bank environmental safeguards can be traced back to Paragraphs 6 and 21 of the EBRD’s 2003 Environmental Policy, see PCM, Compliance Review Report: D1 Motorway, Phase 1, Slovak Republic (Request No. 2010/01), paras. 8-10 and 12. ...
EBRD Project Complaint Mechanism - Slovenia -
Complaint > Sostanj Thermal Power Plant
Eligibility: Eligibility Assessment Report
EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT PROJECT COMPLAINT MECHANISM ELIGIBILITY ASSESSMENT REPORT COMPLAINT: SOSTANJ THERMAL POWER PROJECT REQUEST NUMBER: 2012/03 Table of contents Executive Summary 1 I. Overview of the Eligibility Assessment process 2 II. Factual Background of the Sostanj Thermal Power Plant PCM Proceeding 6 III. Steps Taken in Determining Eligibilit...