Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

5 Results

Showing Only Project Document (Show All Results)

Top Results By:

  1. Complaint > Petroleum Development and Pipeline Project, Management of the Petroleum Economy Project, and Petroleum Sector Management Capacity Building Project

    Project Document: Chad-Cameroon Petroleum Development and Pipeline Project Implementation Completion Report

    ...compensations Le plan de compensation pr�voyait des compensations individuelles, communautaires et r�gionales. Les r�alisations en mati�re de compensations sont les suivantes : Compensations individuelles : Au premier trimestre de l'ann�e 2005, le montant des compensations individuelles vers�es � 4 130 exploitants est �valu� � 9,7 millions de Dollars US (5,4 Milliards FCFA). Compensations communautaires et r�gionales : Ces compensations avaient quasiment toutes �t� ex�cut�es au 31 mai ...

    WB Inspection Panel - Chad - 2006
  2. Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit

    Project Document: Nepal Arun III Cancellation Note

    ...compensation for each family was determined in accordance with the ACRP (para 6.d). Compensations were paid to 1,352 PAFs. Despite advance notification to the villagers to collect the compensation amount, as required by the approved guidelines for acquisition of land and distribution of compensation, 283 families did not claim the compensation money. HMG stated that the compensation amount was deposited in an escrow account. When it was decided that the 'hill" road was not going to be built...

    WB Inspection Panel - Nepal - 1996
  3. Complaint > Petroleum Development and Pipeline Project, Management of the Petroleum Economy Project, and Petroleum Sector Management Capacity Building Project

    Project Document: Chad-Cameroon Petroleum Development and Pipeline Project Overview

    ...compensation measures. 131. The costs of environmental and social mitigation measures, including the resettlement program, were not clearly provided for in the final EMP. The actual costs of compensation provided to individuals and communities were challenged in many instances, and NGOs were skeptical about the costs of some mitigation measures and compensation provided to affected peoples and communities. This could have been avoided by a clear itemization and description in th...

    WB Inspection Panel - Chad - 2006
  4. Complaint > Petroleum Development and Pipeline Project, Management of the Petroleum Economy Project, and Petroleum Sector Management Capacity Building Project

    Project Document: Chad-Cameroon Petroleum Development and Pipeline Project Program Performance and Assessment Report

    ...compensation programs in both countries. Villages received community compensation, such as water wells and water points, electrification, community centers, schools, etc. Individuals were compensated for lost land, trees, and other types o f property. In Cameroon, the COTCO-PSMC-NGO platform for cooperation and grievance resolution began operations to ensure that compensation programs were delivered as intended. During the construction phase, COTCO implemented a compensation program for in...

    WB Inspection Panel - Chad - 2009
  5. Complaint > Gibe III Hydroelectric Power Project

    Project Document: FINAL DRAFT REPORT ON SOCIO – ECONOMIC ANALYSIS AND PUBLIC CONSULTATION OF LAKE TURKANA COMMUNITIES IN NORTHERN KENYA

    ...cash on time. The coordinator of safety net program approves eligible beneficiaries and summit the list to equity bank. Equity Bank issues smart cards and distributes to beneficiaries. With villager spread out over vast areas of often arid land, many community members cannot access equity bank. A network of shopkeepers with adequate cash flows are selected to make payment on behalf of program using machines called Point of sale. Monitoring and Evaluation is also done 5 Riam Riam This is ...

    AfDB Independent Recourse Mechanism - Ethiopia - 2009