DocSearch | Accountability Console
Complaints IAMs Register Login

Loading...

Document Search

Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

3 Results

Showing Only Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project (Show All Results)

Top Results By:

  1. Complaint > Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project

    Compliance Report: 24-Investigation Report (English)

    ...compensation package which ended up setting payment caps to limit exposure to fraud. Can one estimate the number of PAPs who lost compensation because they succumbed to offers of cash by speculators who purchased part or all of their holdings? Can one estimate the number of PAPs who allowed speculators to pose as tenants thereby foregoing the crop compensation they would otherwise have had? ...

    WB Inspection Panel - Uganda - 2001
  2. Complaint > Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project

    Management Response: 24-Management Response (English)

    ...compensation for lost crops and land. 61. Receipt of a resettlement plan, including details of compensation proposals, was required prior to an invitation being sent to negotiate the Credit, and implementation of the plan was a condition of disbursement for the civil works component of the project. In March 1992, the Relocation and Compensation Plan Final Report for Owen Falls Extension (following on the January 1991 UEB submittal) was finalized (for a much larger number of households than f...

    WB Inspection Panel - Uganda - 2001
  3. Complaint > Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project

    Other: 24-Annexes to Management Report and Recommendation

    ...Compensation for Tourism: In failing to ensure 8.6, OD Comment: Loss of tourism income and employment was dealt that compensation was paid, and/or rehabilitation 301- 4.30 with in two ways: (1) at the level of the tourism enterprises or op- was provided, to people who will lose their primary 307 erators; and (2) at the level of project-affected individuals deriving sources of income as a result of the Project’s im- income from touri...