Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Document Search
Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.
4 Results
Showing Only Alto Maipo Hydroelectric Power Project (Show All Results)
Top Results By:
-
Complaint > Alto Maipo Hydroelectric Power Project
Management Response: Management Response
...climate change will increase the surface run-off so as to counteract any decrease in flow rates even in the most unfavorable scenario; and (iii) projected water flows even after climate change variables have been accounted for will be sufficient to guarantee all currently existing water rights. The operation of the project will have to be adjusted for those changes, ensuring at all times that the pre- ...
IDB Independent Consultation and Investigation Mechanism - Chile - 2017 -
Complaint > Alto Maipo Hydroelectric Power Project
...climate change and desertification 2) Ten consecutive years of drought in the basin affected by the project 3) Real flow rates of the rivers that will be affected 4) Effects on la sedimentology of the river 5) Effects of the project on glaciers and groundwater 1 See: http://www.iadb.org/en/projects/project-description-title,1303.html?id=CH%2DL1067 2 Source: Annex 08. River Basin Management and Climate Change. The case of the Maipo. 3 La ECR is the environmental permit o...
IDB Independent Consultation and Investigation Mechanism - Chile - 2017 -
Complaint > Alto Maipo Hydroelectric Power Project
Eligibility: Eligibility Memorandum Public Disclosure
...climate change. Likewise, studies had been done on the potential impact of climate change on the project, and the project’s operation - 10 - will have to be adjusted for those changes, ensuring that the pre-established environmental flow rates are respected at each intake point. 3.9 Additionally, the sediment monitoring program adopted by the project will track hydraulic p...
IDB Independent Consultation and Investigation Mechanism - Chile - 2017 -
Complaint > Alto Maipo Hydroelectric Power Project
...climate change. Likewise, studies were done on the potential impact of climate change on the project, and the project’s operation will have to be adjusted for those changes, ensuring that the pre-established environmental flow rates are respected at each intake point. 4.7 Additionally, the sediment monitoring program adopted by the project will track hydraulic profiles downriver, so that control measures can be activated to guarantee water flow. 4.8 ...
IDB Independent Consultation and Investigation Mechanism - Chile - 2018
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.