Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

6 Results

Showing Only Power Development Project (Show All Results)

Top Results By:

  1. Complaint > Power Development Project

    Timeline: 87-Register (English)

    ...Request for Inspection received by Secretariat July 10, 2013 2. Request Registered July 24, 2013 3. Notice of Registration with the Request sent to the July 24, 2013 President 4. Notice of Registration sent to: 5. Requesters July 24, 2013 6. Executive Directors July 24, 2013 7. Notice of Registration put on the IPN website July 24, 2013 8. Executive Director representin...

    WB Inspection Panel - Nepal - 2013
  2. Complaint > Power Development Project

    Registration: 87-Notice of Registration (English)

    ...Request for Inspection Nepal: Power Development Project (P043311) Receipt of Request On July 10, 2013, the Inspection Panel received a Request for Inspection (hereafter "the Request") related to the Nepal: Power Development Project (PDP, "the Project"), and specifically its 220 kV Khimti-Dhalkebar Transmission Line (KDTL) under its Component C. The Requesters The Request was submitted by 103...

    WB Inspection Panel - Nepal - 2013
  3. Complaint > Power Development Project

    Management Response: 87-Update-Management Action Plan (English)

    ...REQUEST FOR INSPECTION 4. The Request for Inspection was submitted by 103 indigenous and non-indigenous families in three villages of Sindhuli District, supported by a coalition of civil society organi- zations and individuals. The Requesters’ key claims were that the PDP had not complied with the Bank’s policies in relation to: (i) analysis and due consideration of alternatives in the alignment of the Khimti-Dhalbekar Transmission Line and the corresponding potential ad- verse impacts ass...

    WB Inspection Panel - Nepal - 2013
  4. Complaint > Power Development Project

    Eligibility: 87-Management Report and Recommendation - Nepal Power Development Project

    ...Request for Inspection, IPN Request RQ 13/5 (hereafter referred to as “the Request”), concerning the Nepal Power Development Project (PDP, or “the Project”) financed by the International Development Association (the Bank). The Request for Inspection was submitted by 103 indigenous and non-indigenous families in three villages of Sindhuli District supported by a coalition of civil society organizations and individuals (“the Requesters”). The Requesters authorized a lawyer from the Lawyers’ Associ...

    WB Inspection Panel - Nepal - 2013
  5. Complaint > Power Development Project

    Compliance Report: 87-Investigation Report-Nepal Power Development Project

    ...Requesters originate. C. Summary of the Request for Inspection and Management Response C1. Requesters Claims 11. A summary of the allegations stated in the Request is provided below. The complete Request is available on the Panel website. 13 12. Inadequate Study of Alternatives. The Requesters demand that the transmission line be “realigned to an alternative route where there is no human settlement,” thus avoiding re-location and minimizing damage to cultural properties to t...

    WB Inspection Panel - Nepal - 2013
  6. Complaint > Power Development Project

    Management Response: 87-Management Response (English)

    ...REQUEST 3. The Request for Inspection was submitted by 103 indigenous and non-indigenous families in three villages of Sindhuli District supported by a coalition of civil society or- ganizations and individuals (“the Requesters”). The Requesters have authorized an advo- cate at the Lawyers’ Association for the Human Rights of Nepalese Indigenous Peoples (“LAHURNIP”) to represent them. 4. Attached to the Request are: (i) A copy of the email addressed to the Inspection Panel ...

    WB Inspection Panel - Nepal - 2013