Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

6 Results

Showing Only Land Management and Administration Project (Show All Results)

Top Results By:

  1. Complaint > Land Management and Administration Project

    Eligibility: 60-Management Report and Recommendations Map 4

    ...UNKNOWN Battambang COMMUNES IN WHICH LAND TITLING OCCURRED M ekong 13° N ...

    WB Inspection Panel - Cambodia - 2009
  2. Complaint > Land Management and Administration Project

    Eligibility: 60-Management Report and Recommendations Map 2

    ...UNKNOWN Thailand PROVINCE Sras Chok COMMUNES IN WHICH LAND TITLING OCCURRED Ruessei Kaev Rues...

    WB Inspection Panel - Cambodia - 2009
  3. Complaint > Land Management and Administration Project

    Compliance Report: 60-Investigation Report (English)

    ...unknown, the Panel is extremely concerned about the large number of people who were forcibly evicted, displaced, or are under threat of eviction in Project areas. The Panel found that due to lack of a robust monitoring and evaluation system for the Project, Bank Management did not become aware of significant issues arising from the Project, which does not comply with Bank policy. Additional Observations. The Panel wishes to underscore that it considers the Bank’s engagement on land issues in Cam...

    WB Inspection Panel - Cambodia - 2009
  4. Complaint > Land Management and Administration Project

    Eligibility: 60-Management Report and Recommendation (English)

    ...unknown”5 ownership. 22. Negotiations between the Government and a private developer had started in 2005. Despite assertions that the land in question was State Public Land, and hence could not be claimed through legal possession by residents, plans for private development of the BKL area were well advanced prior to the declaration of the area as an Adjudication Area. Copies of 4 Management requested a Lead Counsel from the Environmental and International Law Unit (LEGEN), and a Se...

    WB Inspection Panel - Cambodia - 2009
  5. Complaint > Land Management and Administration Project

    Eligibility: 60-Eligibility Report (English)

    ...unknown”, which seems to be the classification that is generally used for State Public Land in a titling process. However, Management also adds that based on information it gathered, only the villages around BKL area were demarcated and no demarcation of individual parcels took place. Moreover, only one title (for a public gas depot) was issued in the 12 Management Response, ¶ 95. 13 Management Response, ¶ 48. 14 Management Response, ¶ 48. ...

    WB Inspection Panel - Cambodia - 2009
  6. Complaint > Land Management and Administration Project

    Management Response: 60-Management Response (English)

    ...unknown”. This appears to be the classification that is generally used when State Public Land is encountered during the titling process as well as when land is subject to a dispute that cannot be resolved during the titling process at the field level. • On the basis of information currently available, it seems that only one title was issued in the name of the State as a result of the systematic adjudication process. Management understands that one title wa...

    WB Inspection Panel - Cambodia - 2009