Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

3 Results

Showing Only Boskov Most Hydro Power (Show All Results)

Top Results By:

  1. Complaint > Boskov Most Hydro Power

    Eligibility: Eligibility Assessment Report

    ...wind, solar and sustainable biomass have not been properly assessed and the area for the project could be considered a “critical” habitat by virtue of the proven presence of the Balkan lynx in the Project area, which, according to Macedonian scientists, is a critically endangered species. During discussions in Skopje on 7th February 2012, the Complainant provided further information comprising maps showing current and proposed zoning of the Mavrovo ...

    EBRD Project Complaint Mechanism - Macedonia
  2. Complaint > Boskov Most Hydro Power

    Filing: Complaint

    ...wind, solar and sustainable biomass, there are certainly technically and economically feasible alternatives to the project. However the alternatives have not been properly assessed due to the lack of Strategic Environmental Assessment of the Strategy for renewable use of energy sources of the Republic f Macedonia. PR 6.13: Irrespective of whether it is natural or modified, some habitat may be considered to be critical by virtue of (i) its high biodiversity value; (ii) its impor...

    EBRD Project Complaint Mechanism - Macedonia
  3. Complaint > Boskov Most Hydro Power

    Compliance Report: Compliance Review Report

    ...wind, solar and sustainable biomass have not been properly assessed and the area for the project could be considered a “critical habitat” by virtue of the proven presence of the Balkan lynx in the Project area, which according to Macedonian scientists is a critically endangered species. d) The original Complaint further alleges that a Strategic Environmental Assessment (SEA) has not been prepared for the relevant strategy on renewable energy as is required ...