Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

4 Results

Showing Only Krnovo Wind Farm (Show All Results)

Top Results By:

  1. Complaint > Krnovo Wind Farm

    Eligibility: Eligibility Assessment Report

    ...Wind Farm Project, available at http://www.ebrd.com/work-with- us/projects/psd/krnovo-wind-farm.html. 4 III. SUMMARY OF THE RELEVANT PARTIES’ VIEWS 1. Complainant 8. The Complainant initially contacted PCM on 7 August 2015 via email, stating that he owns 21,100 m² of land in Krnovo, Montenegro, where the Krnovo Wind Farm was going to be constructed with financial support from EBR...

    EBRD Project Complaint Mechanism - Montenegro
  2. Complaint > Krnovo Wind Farm

    Compliance Report: Compliance Review Report

    ...wind farm project, June 2016, p. 5. Not publicly available. 59 Id. 60 Ledec, George C.; Rapp, Kennan W.; Aiello, Roberto G. 2011. Greening the wind: environmental and social considerations for wind power development (English). A World Bank study. Washington, DC: World Bank, p. 82, available at: http://documents.worldbank.org/curated/en/239851468089382658/Greening- the-wind-environmental-and-social-considerations-for-wind-power-development (Last accessed 11 February 2018). ...

    EBRD Project Complaint Mechanism - Montenegro
  3. Complaint > Krnovo Wind Farm

    Filing: Complaint

    ...Wind Farm Please describe the harm that has been caused or might be caused by the Project. Project Sponsor did not try to acquire land rights through negotiation but through expropriation which is not in compliance with EBRD's Environmental and Social Policy. Project Sponsor did not contact me until I reached out to EBRD. Project Sponsor intended to expropriate only the area where the towers will be built but not the area under power wires and adjacent area that will be unusable completely for s...

    EBRD Project Complaint Mechanism - Montenegro
  4. Complaint > Krnovo Wind Farm

    Timeline: Processing steps

    ...Wind Farm Project number: 44546 Country: Montenegro Step Date Remarks 1. Complaint received by the 2 March 2017 Complaint is received by PCM Officer. email. 2. Complaint is registered 6 March 2017 according to PCM RPs 11-13. Relevant parties are informed. 3. PCM Expert Susan Wildau is 7 March 2017 appointed as Eligibility Assessment Expert for the Complaint. Her ass...

    EBRD Project Complaint Mechanism - Montenegro