Project Information
Investment ID:
Bank:
Environmental Category: A
Country: Egypt
Region: Middle East and North Africa
Approval Date: Sept. 29, 2017
Investment Types:
Total Project Cost: USD 75.0 million
Total Complaints: 0
Description
The project is a greenfield 50 MW photovoltaic (PV) plant being developed by Alcazar Energy Partners (the sponsor) with Enerpal International S.L.U (Enerpal) as a technical consultant. The sponsor will own the project company “Alcazar Energy Egypt Solar 1 SAE”. The Engineering, Procurement & Construction (EPC) Contractor will be a joint venture between TSK and Enviromena, who will also undertake the role of the Operations and Maintenance (O&M) for this project. Environmena was established in Abu Dhabi in 2007, as the first downstream solar company in the Middle East and North Africa. TSK was established as a public company in 1986 and began working in the solar PV field since 2006.
Investments
Investment Type | ID | Amount | Status | Bank | Client |
---|
Related Complaints
Implementers
Name | Complaints | Dispute Resolutions | DR Successful | Compliance Reviews | Non-Compliance |
---|---|---|---|---|---|
CTGI RENEWBLE ENERGY EGYPT SOLAR 1 SAE |