Akiira I Geothermal Power Plant

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Project

Name: Akira I Geothermal Power Plant

Investments: EIB

Client:

Support:

Country: Kenya

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2018/36/PR

Date Filed: Aug. 31, 2018

Date Closed: March 28, 2019

Status: Closed With Outputs Outside Process

Description

Alleged negative environmental and social impacts.

Complaint Stages

Filing

Aug. 31, 2018

Filing

Status:

Start Date: Aug. 31, 2018

Registration

Aug. 31, 2018 -

Sept. 13, 2018

Registration

Status: Closed With Output

Start Date: Aug. 31, 2018

End Date: Sept. 13, 2018

Eligibility

Closed With Output

Eligibility

Status: Closed With Output

Explanation: Inadequate information, Early-stage project; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

March 28, 2019

Timeline