Autobahn A49 Fritzlar-Ohmtal Dreieck (PPP) | Accountability Console
Complaints IAMs Register Login

Loading...

Autobahn A49 Fritzlar-Ohmtal Dreieck (PPP)

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 116

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 451

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 429

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 320

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 200

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 741

Browse Complaints

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2021/02

Date Filed: Feb. 2, 2021

Status: Active

Description

Alleged negative environmental impacts of the project

Complaint Stages

Filing

Feb. 2, 2021

Filing

Status:

Start Date: Feb. 2, 2021

Registration

Feb. 2, 2021 -

Feb. 4, 2021

Registration

Status: Closed With Output

Start Date: Feb. 2, 2021

End Date: Feb. 4, 2021

Eligibility

Feb. 4, 2021 -

July 8, 2021

Eligibility

Status: Closed With Output

Start Date: Feb. 4, 2021

End Date: July 8, 2021

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary

Compliance Review

July 8, 2021

Compliance Review

Status: In Progress

Start Date: July 8, 2021

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Compliance Review in progress

Closed

Not Closed

Timeline