Castor Underground Gas Storage | Accountability Console
Complaints IAMs Register Login

Loading...

Castor Underground Gas Storage

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Project

Name: Castor Underground Gas Storage

Investments: EIB

Client:

Support: Loans

Country: Spain

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2013/12

Date Filed: Dec. 3, 2013

Date Closed: June 30, 2022

Status: Closed With Outputs

Description

On 3 December 2013, the EIB Complaints Mechanism (EIB-CM) received a complaint from the Plataforma Ciutadana en Defensa de les Terres del Sènia. The allegations relate to the environmental and social impacts of the project as well as the way the public consultation was carried out. The complainant was also concerned about the risks associated with the induced seismicity of the project as well as other industrial risks.

Complaint Stages

Filing

Dec. 3, 2013

Filing

Status:

Start Date: Dec. 3, 2013

Registration

Dec. 3, 2013 -

Dec. 4, 2013

Registration

Status: Closed With Output

Start Date: Dec. 3, 2013

End Date: Dec. 4, 2013

Eligibility

Dec. 4, 2013 -

May 4, 2015

Eligibility

Status: Closed With Output

Start Date: Dec. 4, 2013

End Date: May 4, 2015

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage; Unknown

Compliance Review

May 4, 2015 -

March 23, 2018

Compliance Review

Status: Closed With Output

Start Date: May 4, 2015

End Date: March 23, 2018

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

March 23, 2018 -

June 30, 2022

Monitoring

Status: Closed With Output

Explanation: Mechanism deemed involvement unnecessary; Funding and/or consideration ended

Closed

June 30, 2022

Timeline

Documents

Name Category Description
Compliance Review Compliance Review