Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Cusco Transport Improvement Project (P132505)
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Retaliation (actual or feared)
Description: Complaint raises concerns about incidents or risk of harm against those who have raised concerns about the project perpetrated by the project company, government, public or private security forces, or other individuals acting on behalf of project proponents. Retaliation may include discrimination, slander, threats, denial of services, unfounded judicial proceedings, and termination of employment. Concerns regarding specific incidents of violence are not included.
Complaints with this Issue: 71
Violence against the community
Description: Complaint raises concerns about incidents of violence against community members or activists perpetrated by the project company, government, public or private security forces, or other individuals acting on behalf of project proponents.
Complaints with this Issue: 51
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Cusco Transport Improvement Project
Investments: WB P132505
Client: COPESCO, Ministerio de Economia y Finanzas - MEF, Peru
Support: Loans
Country: Peru
Complaint
ID: 148
Date Filed: July 16, 2020
Date Closed: Jan. 12, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
July 16, 2020
Filing
Status:
Start Date: July 16, 2020
Registration
July 16, 2020 -
Sept. 28, 2020
Registration
Status: Closed With Output
Start Date: July 16, 2020
End Date: Sept. 28, 2020
Eligibility
Sept. 28, 2020 -
Jan. 12, 2021
Eligibility
Status: Closed With Output
Explanation: Good faith requirement not met; Outside of mandate, Inadequate link between bank action and harm alleged
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Jan. 12, 2021
Timeline