Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Flood Emergency Reconstruction and Resilience Project 2
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 538
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Flood Emergency Reconstruction and Resilience Project
Investments: ADB 49038-001
Client: Ministry of Kashmir Affairs and Northern Areas, Planning & Dev. Dept., Govt. of the Punjab, Planning & Development Department (P&D)
Support: Advisory services, Loans
Country: Pakistan
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: Sept. 24, 2021
Date Closed: Oct. 20, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Sept. 24, 2021
Filing
Status:
Start Date: Sept. 24, 2021
Registration
Sept. 24, 2021 -
Sept. 27, 2021
Registration
Status: Closed With Output
Start Date: Sept. 24, 2021
End Date: Sept. 27, 2021
Eligibility
Sept. 27, 2021 -
Oct. 20, 2021
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Oct. 20, 2021
Timeline
Documents
Name | Category | Description |
---|---|---|
Complaint Letter | Filing |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Flood Emergency Reconstruction and Resilience Project | ADB SPF CRP | Pakistan | 02/06/2018 | Closed Without Outputs |