General San MartÃn Railroad Improvement Project: Retiro-Pilar Branch Line
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Sectors
Community capacity and development
Description: Project relates to programs targeted at training, capacity-building, and/or enabling public participation for specific groups within the community.
Complaints in this Sector: 112
Conservation and environmental protection
Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.
Complaints in this Sector: 62
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: General San MartÃn Railroad Improvement Project: Retiro-Pilar Branch Line
Investments: IDB 4265/OC-AR
Client:
Support: Loans
Country: Argentina
Complaint
IAM: Independent Consultation and Investigation Mechanism (MICI)
Date Filed: Nov. 19, 2022
Date Closed: April 6, 2023
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Nov. 19, 2022
Filing
Status:
Start Date: Nov. 19, 2022
Registration
Nov. 19, 2022 -
Dec. 6, 2022
Registration
Status: Closed With Output
Start Date: Nov. 19, 2022
End Date: Dec. 6, 2022
Eligibility
Dec. 6, 2022 -
April 6, 2023
Eligibility
Status: In Progress
Start Date: Dec. 6, 2022
End Date: April 6, 2023
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
April 6, 2023
Timeline
Documents
Name | Category | Description |
---|---|---|
Eligibility Determination | Eligibility | |
Eligibility Extension | Eligibility |