GEORGIA - Jvari-Khorga Interconnection
Issues
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Project
Name: GEORGIA - Jvari-Khorga Interconnection
Investments: EBRD 45181
Client: Georgian State Electrosystem (GSE), Government of Georgia
Support: Loans
Country: Georgia
Complaint
IAM: Project Complaint Mechanism (PCM)
ID: 2017/02
Date Filed: April 21, 2017
Date Closed: Dec. 31, 2018
Status: Closed With Outputs
Complaint Stages
Filing
April 21, 2017
Filing
Status:
Start Date: April 21, 2017
Registration
April 21, 2017 -
May 8, 2017
Registration
Status: Closed With Output
Start Date: April 21, 2017
End Date: May 8, 2017
Eligibility
May 8, 2017 -
Aug. 24, 2017
Eligibility
Status: Closed With Output
Start Date: May 8, 2017
End Date: Aug. 24, 2017
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Aug. 28, 2017 -
July 20, 2018
Compliance Review
Status: Closed With Output
Start Date: Aug. 28, 2017
End Date: July 20, 2018
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
July 20, 2017 -
Dec. 31, 2018
Monitoring
Status: Closed With Output
Start Date: July 20, 2017
End Date: Dec. 31, 2018
Closed
Dec. 31, 2018
Timeline
Documents
Commitments
Type | Category | Description | Status |
---|---|---|---|
Process Change | Operations Management | Contractor Procurement Process | Accomplished |