Complaints | Accountability Console
Complaints IAMs Register Login

Loading...

Complaint Country: Georgiax

Complaints

A complaint is a submission to an independent accountability mechanism that raises concerns about actual or potential harm related to an IFI-supported project.


Complaint Filters

IAM
Status
Issue
Filer Type
is registered
Is eligible
Has DR Agreement
Non-Compliance Found
Is monitored
Complaint Country
Complaint Region
Rejection Reasons
Year Filed
Year Closed
Min Duration (months)
Max Duration (months)

Complaint Stage Filters

Registration Outputs
Has registration report
Unregistered - Reasons
Eligibility Outputs
Has eligibility report
Ineligibility - Reasons
Dispute Resolution Outputs
Has dr report
No DR - Reasons
Compliance Review Outputs
Has compliance report
No CR - Reasons
Monitoring Outputs
Has monitoring report
No Monitoring - Reasons

Project Filters

Bank
Project
Client
Implementer
Sector
Investment Type
Project Country
Project Region
Clear
Asian Development Bank SPF CRP Complaints IAM Country Date Filed Status
Sustainable Urban Transport Investment Program ADB SPF CRP Georgia 27/10/2010 Closed Without Outputs
Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 21/05/2018 Closed Without Outputs
Nenskra Hydropower Project ADB SPF CRP Georgia 18/11/2017 Closed Without Outputs
Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 29/01/2016 Monitoring
Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 26/10/2016 Closed Without Outputs
Adjaristsqali Hydropower Project ADB SPF CRP Georgia 15/02/2018 Closed Without Outputs
Batumi Bypass Road Project ADB SPF CRP Georgia 21/08/2017 Closed Without Outputs
MFF-Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 28/07/2017 Closed Without Outputs
MFF-Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 11/06/2017 Closed Without Outputs
MFF-Sustainable Urban Transport Investment Program - Tranche 3 (Section 2, Part B of the Tbilisi-Rustavi Urban Road Link) ADB SPF CRP Georgia 13/03/2017 Closed Without Outputs
MFF Sustainable Urban Transport Investment Program - Tranche 2 (3rd section of Tbilisi-Rustavi Road) ADB SPF CRP Georgia 26/10/2016 Closed Without Outputs
MFF Sustainable Urban Transport Investment Program - Tranche 2 (Section 3) ADB SPF CRP Georgia 20/10/2016 Closed Without Outputs
MFF Sustainable Urban Transport Investment - Program Tranche 3 ADB SPF CRP Georgia 13/05/2016 Closed Without Outputs
MFF Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 12/04/2016 Closed Without Outputs
Batumi Bypass Road project ADB SPF CRP Georgia 25/07/2018 Closed With Outputs
Sustainable Urban Transport Investment Program - Tranche 3 ADB SPF CRP Georgia 21/08/2018 Closed With Outputs
North-South Corridor (Kvesheti-Kobi) Road Project ADB SPF CRP Georgia 16/10/2019 Closed Without Outputs
North-South Corridor (Kvesheti-Kobi) Road Project ADB SPF CRP Georgia 06/01/2021 Monitoring
Batumi Bypass Road Project ADB SPF CRP Georgia 25/08/2022 Closed Without Outputs
IFC/MIGA CAO Complaints IAM Country Date Filed Status
BTC Pipeline-01/ Switzerland IFC CAO Azerbaijan, Georgia, Turkey 01/12/2003 Closed Without Outputs
BTC Pipeline-02/Rustavi IFC CAO Georgia 16/03/2004 Closed With Outputs
BTC Pipeline-03/Switzerland IFC CAO Georgia 01/03/2004 Closed Without Outputs
BTC Pipeline-04/Switzerland IFC CAO Georgia 01/05/2004 Closed Without Outputs
BTC Pipeline-05/Rustavi City IFC CAO Georgia 01/05/2004 Closed Without Outputs
BTC Pipeline-06/Bashkovi IFC CAO Georgia 21/05/2004 Closed Without Outputs
BTC Pipeline-07/Dgvari IFC CAO Georgia 21/05/2004 Closed With Outputs Outside Process
BTC Pipeline-08/Sagrasheni IFC CAO Georgia 21/05/2004 Closed Without Outputs
BTC Pipeline-09/Tetritskaro IFC CAO Georgia 29/05/2004 Closed Without Outputs
BTC Pipeline-10/Tetritskaro IFC CAO Georgia 21/05/2004 Closed With Outputs
BTC Pipeline-11/Tsikhisjvari IFC CAO Georgia 21/05/2004 Closed Without Outputs
BTC Pipeline-12/Tba, Tsemi, Sadgeri IFC CAO Georgia 28/05/2004 Closed With Outputs Outside Process
BTC Pipeline-13/Tsalka IFC CAO Georgia 22/07/2004 Closed With Outputs Outside Process
BTC Pipeline-14/Vale IFC CAO Georgia 08/08/2004 Closed With Outputs
BTC Pipeline-15/Tetritsakro IFC CAO Georgia 01/12/2004 Closed Without Outputs
BTC Pipeline-16/Tetritsakro IFC CAO Georgia 01/12/2004 Closed Without Outputs
BTC Pipeline-17/Tadzrisi IFC CAO Georgia 10/12/2004 Closed With Outputs
BTC Pipeline-18/Tetritsakro IFC CAO Georgia 01/12/2004 Closed Without Outputs
BTC Pipeline-19/Atskuri Temple IFC CAO Georgia 03/05/2005 Closed Without Outputs
BTC Pipeline-20/Atskuri IFC CAO Georgia 03/05/2005 Closed Without Outputs
BTC Pipeline-22/Tsemi IFC CAO Georgia 24/06/2005 Closed With Outputs
BTC Pipeline-23/Tsemi IFC CAO Georgia 24/06/2005 Closed Without Outputs
BTC Pipeline-24/Vale IFC CAO Georgia 01/08/2005 Closed Without Outputs
BTC Pipeline-25/Vale IFC CAO Georgia 01/08/2005 Closed Without Outputs
BTC Pipeline-26/Krstanisi IFC CAO Georgia 12/12/2005 Closed Without Outputs
BTC Pipeline-27/Tbilisi IFC CAO Georgia 15/06/2006 Closed Without Outputs
BTC Pipeline-29/Tsalka IFC CAO Georgia 03/08/2006 Closed With Outputs
BTC Pipeline-30/Vale IFC CAO Georgia 20/08/2007 Closed With Outputs
BTC Pipeline-31/Naokhrebi IFC CAO Georgia 28/02/2008 Closed Without Outputs
BTC Pipeline-32/Vale IFC CAO Georgia 01/08/2008 Closed With Outputs
BTC Pipeline-33/Vale IFC CAO Georgia 30/05/2011 Closed With Outputs
AGL-01/Makhalakidzeebi IFC CAO Georgia 15/02/2018 Active
Trans-Anatolian Pipeline-01/Vale IFC CAO Azerbaijan, Georgia, Turkey 29/03/2017 Closed Without Outputs
TANAP-02/Garajemirli IFC CAO Azerbaijan, Georgia, Turkey 26/10/2018 Closed Without Outputs
BP Georgia-01/Tbilisi IFC CAO Georgia 01/11/2018 Closed Without Outputs
Overseas Private Investment Corporation OA Complaints IAM Country Date Filed Status
Baku - Tbilisi - Ceyhan Pipeline OPIC OA Georgia 01/03/2006 Closed With Outputs