Metro of Bogota First Line - First tranch

Issues

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 215

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Description

The Request describes a potential damage to the Requesters property derived from a possible incomplete appraisal during the expropriation process contemplated by the Project for its construction. Specifically, it is alleged that the final amount offered would not include all the surfaces owned by the Requests and that the price per appraised square meter would be lower than the market price.

Complaint Stages

Filing

Aug. 6, 2020

Filing

Status:

Start Date: Aug. 6, 2020

Registration

Aug. 6, 2020 -

Aug. 12, 2020

Registration

Status: Closed With Output

Explanation: Good faith requirement not met

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Aug. 12, 2020

Timeline