Mumbai Metro Line 4 (Wadala – Kasarvadavali) Project | Accountability Console
Complaints IAMs Register Login

Loading...

Mumbai Metro Line 4 (Wadala – Kasarvadavali) Project

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 526

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Project

Name: Mumbai Metro Line 4 Project

Investments: AIIB 000029

Client:

Support: Loans

Country: India

Complaint

IAM: Project-affected People’s Mechanism (PPM)

ID: 1

Date Filed: June 19, 2019

Date Closed: June 20, 2019

Status: Closed Without Outputs

Complaint Stages

Filing

June 19, 2019

Filing

Status:

Start Date: June 19, 2019

Registration

June 19, 2019 -

June 19, 2019

Registration

Status: Closed Without Output

Start Date: June 19, 2019

End Date: June 19, 2019

Eligibility

June 20, 2019 -

June 20, 2019

Eligibility

Status: Closed Without Output

Explanation: Outside of mandate, Alleged bank action did not occur; Filer Issue, Complaint filed by only 1 individual

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

June 20, 2019

Timeline