Nyakararo - Mwaro - Gitega Road (RN18) Upgrade and Asphalting Project / Phase II, Troncon Kibumbu-Gitega (Mweya): 24 Km | Accountability Console
Complaints IAMs Register Login

Loading...

Nyakararo - Mwaro - Gitega Road (RN18) Upgrade and Asphalting Project / Phase II, Troncon Kibumbu-Gitega (Mweya): 24 Km

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 538

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Complaint

IAM: Independent Recourse Mechanism (IRM)

ID: RQ2021/1

Date Filed: Jan. 6, 2021

Date Closed: May 22, 2021

Status: Closed With Outputs

Description

On 6 January 2021, the Compliance Review and Mediation Unit (BCRM) received, through the Country Manager of the Bank Office in Burundi, a Complaint relating to the Nyakararo Mwaro –Gitega (RN18 /Phase II, Kibumbu-Gitega (Mweya): 24 km road project in Burundi. BCRM, in its preliminary assessment of the complaint, realized that the complaint did not meet the criteria for registration as it was submitted by one affected individual without the power of representation of other affected people. Following several exchanges with the Complainant, BCRM received on 5 February 2021 the representational authority and a confirmation that the issues raised in the complaint are not pending before any national court.

Complaint Stages

Filing

Jan. 6, 2021

Filing

Status:

Start Date: Jan. 6, 2021

Registration

Jan. 6, 2021 -

Feb. 22, 2021

Registration

Status: Closed With Output

Start Date: Jan. 6, 2021

End Date: Feb. 22, 2021

Eligibility

Feb. 22, 2021 -

June 3, 2021

Eligibility

Status: Closed With Output

Explanation: Complaint not yet reached stage, Eligibility in progress

Dispute Resolution

June 3, 2021 -

Sept. 9, 2021

Dispute Resolution

Status: Closed With Output

Explanation: Complaint not yet reached stage, Eligibility in progress

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Eligibility in progress

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Eligibility in progress

Closed

May 22, 2021

Timeline