PV Hybrid Storage System Demo Project (EDP)
Issues
Cultural heritage
Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.
Complaints with this Issue: 120
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Project
Name: PV Hybrid Storage System Demo Project (EDP)
Investments: EIB 20190284
Client: HYDROGENE DE FRANCE SAS,MERIDIAM EI SAS,SA DE LA RAFFINERIE DES ANTILLES
Support: Loans
Country: France
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2022/04
Date Filed: Feb. 28, 2022
Date Closed: June 1, 2022
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Feb. 28, 2022
Filing
Status:
Start Date: Feb. 28, 2022
Registration
Feb. 28, 2022 -
March 3, 2022
Registration
Status: Closed With Output
Start Date: Feb. 28, 2022
End Date: March 3, 2022
Eligibility
March 3, 2022 -
May 11, 2022
Eligibility
Status: Closed With Output
Start Date: March 3, 2022
End Date: May 11, 2022
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
May 11, 2022 -
June 1, 2022
Compliance Review
Status: Closed Without Output
Explanation: Funding and/or consideration ended; Outside of mandate, Project not implemented
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Mechanism deemed involvement unnecessary, Mechanism chose not to monitor
Closed
June 1, 2022
Timeline
Documents
Name | Category | Description |
---|---|---|
Final Letter | Eligibility | |
Final Letter (English) | Eligibility |