Rehabilitation of the Railway in Cambodia Project 2 | Accountability Console
Complaints IAMs Register Login

Loading...

Rehabilitation of the Railway in Cambodia Project 2

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 525

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 482

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Project

Name: Rehabilitation of the Railway in Cambodia Project

Investments: ADB

Client:

Support: Loans

Country: Cambodia

Complaint

IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)

ID: SPF-2012-01-02-0040 & 2012/2

Date Filed: April 13, 2012

Date Closed: April 30, 2012

Status: Closed With Outputs

Complaint Stages

Filing

April 13, 2012

Filing

Status:

Start Date: April 13, 2012

Registration

April 13, 2012 -

April 19, 2012

Registration

Status: Closed With Output

Start Date: April 13, 2012

End Date: April 19, 2012

Eligibility

April 19, 2012 -

April 30, 2012

Eligibility

Status: Closed Without Output

Explanation: Good faith requirement not met

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

April 30, 2012

Timeline