Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 384

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 330

Browse Complaints

Sectors

Energy

Description:

Complaints in this Sector: 203

Browse Complaints

Infrastructure

Description:

Complaints in this Sector: 504

Browse Complaints

Complaint

IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)

ID: 3/2006

Date Filed: April 25, 2006

Date Closed: Sept. 30, 2006

Status: Closed Without Outputs

Complaint Stages

Filing

April 25, 2006

Filing

Status:

Start Date: April 25, 2006

Registration

April 25, 2006 -

April 28, 2006

Registration

Status: Completed

Start Date: April 25, 2006

End Date: April 28, 2006

Eligibility

April 28, 2006 -

Sept. 30, 2006

Eligibility

Status: Closed Without Output

Explanation: Good faith requirement not met

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

Sept. 30, 2006

Timeline