São José dos Campos Urban Structuring Program- Request III | Accountability Console
Complaints IAMs Register Login

Loading...

São José dos Campos Urban Structuring Program- Request III

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-BID-BR-2019-0142

Date Filed: Feb. 4, 2019

Date Closed: Nov. 26, 2019

Status: Closed Without Outputs

Description

The Request raises potential impacts on the quality of life of residents located in the area of influence of the Program. Specifically, the Request states that the construction work for the section "Arco da Inovação / Ponte Estaiada," that is part of the Program, would be affecting the property of the inhabitants, by causing the devaluation of properties such as homes and businesses. It also raises possible environmental and health effects in areas that would be impacted by noise, visual and atmospheric pollution; as well as the road insecurity caused by mass transit. Finally, the request alleges that adequate consultation processes did not take place and the information requested about the Project was not provided. The Requesters wish to use both the Consultation Phase and the Compliance Review Phase, in such case that their Request is declared eligible.

Complaint Stages

Filing

Feb. 4, 2019

Filing

Status:

Start Date: Feb. 4, 2019

Registration

Feb. 4, 2019 -

Feb. 12, 2019

Registration

Status: Closed With Output

Start Date: Feb. 4, 2019

End Date: Feb. 12, 2019

Eligibility

Feb. 12, 2019 -

April 26, 2019

Eligibility

Status: Closed With Output

Start Date: Feb. 12, 2019

End Date: April 26, 2019

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not desired by complainant, Complainant chose not to have dispute resolution

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary; Rejected at appraisal or similar; Funding and/or consideration ended

Has Compliance Report: Yes

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

Nov. 26, 2019

Timeline