Second Norte Grande Water Infrastructure Project
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Pollution
Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.
Complaints with this Issue: 229
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Second Norte Grande Water Infrastructure Project
Investments: WB
Client:
Support: Loans
Country: Argentina
Complaint Stages
Filing
May 4, 2011
Filing
Status:
Start Date: May 4, 2011
Registration
May 4, 2011 -
June 29, 2011
Registration
Status: Closed With Output
Start Date: May 4, 2011
End Date: June 29, 2011
Eligibility
June 29, 2011 -
Aug. 31, 2011
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Aug. 31, 2011
Timeline
Documents