Solid Waste Management project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Solid Waste Management project
Investments: UNDP
Client: Government Entity - Ministry - Ministry of Environment
Support:
Country: Lebanon
Complaint
IAM: Social and Environmental Compliance Unit (SECU)
ID: SECU0006
Date Filed: Dec. 19, 2017
Date Closed: April 3, 2018
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Dec. 19, 2017
Filing
Status:
Start Date: Dec. 19, 2017
Registration
Dec. 19, 2017 -
Dec. 27, 2017
Registration
Status: Closed With Output
Start Date: Dec. 19, 2017
End Date: Dec. 27, 2017
Eligibility
Dec. 27, 2017 -
April 3, 2018
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
April 3, 2018
Timeline
Documents
Name | Category | Description |
---|---|---|
Management Action Plan | Management Action Plan |